§ 63.1188 What performance test requirements must I meet?
You must meet the following performance test requirements:
(a) All monitoring systems and equipment must be installed, operational, and properly calibrated before the performance tests.
(b) Conduct a performance test, consisting of three test runs, for each cupola and curing oven or combined collection/curing operation subject to this subpart at the maximum production rate to demonstrate compliance with each of the applicable emissions limits specified in Table 2 to this subpart.
(c) Following the initial performance or compliance test to be conducted within 180 days of the effective date of this rule, you must conduct a performance test to demonstrate compliance with each of the applicable emissions limits specified in Table 2 to this subpart, at least once every 5 years.