§ 75.308 Revision of budget and program plans.
(a) The approved budget for the Federal award summarizes the financial aspects of the project or program as approved during the Federal award process. It may include either the Federal and non-Federal share (see § 75.2 Federal share) or only the Federal share, depending upon HHS awarding agency requirements. It must be related to performance for program evaluation purposes whenever appropriate.
(b) Recipients are required to report deviations from budget or project scope or objective, and request prior approvals from HHS awarding agencies for budget and program plan revisions, in accordance with this section.
(c)
(1) For non-construction Federal awards, recipients must request prior approvals from HHS awarding agencies for one or more of the following program or budget-related reasons:
(i) Change in the scope or the objective of the project or program (even if there is no associated budget revision requiring prior written approval).
(ii) Change in a key person specified in the application or the Federal award.
(iii) The disengagement from the project for more than three months, or a 25 percent reduction in time devoted to the project, by the approved project director or principal investigator.
(iv) The inclusion, unless waived by the HHS awarding agency, of costs that require prior approval in accordance with subpart E of this part, or appendix IX of this part, or 48 CFR part 31, as applicable.
(v) The transfer of funds budgeted for participant support costs as defined in § 75.2 to other categories of expense.
(vi) Unless described in the application and funded in the approved Federal awards, the subawarding, transferring or contracting out of any work under a Federal award, including fixed amount subawards as described in § 75.353. This provision does not apply to the acquisition of supplies, material, equipment or general support services.