§ 63.9641 What reports must I submit and when?
(a) Compliance report due dates. Unless the Administrator has approved a different schedule, you must submit a semiannual compliance report to your permitting authority according to the requirements in paragraphs (a)(1) through (5) of this section.
(1) The first compliance report must cover the period beginning on the compliance date that is specified for your affected source in § 63.9583 and ending on June 30 or December 31, whichever date comes first after the compliance date that is specified for your source in § 63.9583.
(2) On or before January 25, 2021, for affected sources that commenced construction or reconstruction on or before September 25, 2019, the first compliance report must be postmarked or delivered no later than July 31 or January 31, whichever date comes first after your first compliance report is due. After January 25, 2021, for affected sources that commenced construction or reconstruction on or before September 25, 2019, and after July 28, 2020, or upon start-up, which ever date is later, for affected sources that commenced construction or reconstruction after September 25, 2019, the first compliance report must be electronically submitted, postmarked or delivered no later than July 31 or January 31, whichever date comes first after your first compliance report is due.
(3) Each subsequent compliance report must cover the semiannual reporting period from January 1 through June 30 or the semiannual reporting period from July 1 through December 31.
(4) On or before January 25, 2021, for affected sources that commenced construction or reconstruction on or before September 25, 2019, each subsequent compliance report must be postmarked or delivered no later than July 31 or January 31, whichever date comes first after the end of the semiannual reporting period. After January 25, 2021, for affected sources that commenced construction or reconstruction on or before September 25, 2019, and after July 28, 2020, or upon start-up, which ever date is later, for affected sources that commenced construction or reconstruction after September 25, 2019, each subsequent compliance report must be electronically submitted, postmarked or delivered no later than July 31 or January 31, whichever date comes first after the end of the semiannual reporting period.
(5) For each affected source that is subject to permitting regulations pursuant to 40 CFR part 70 or 40 CFR part 71, and if the permitting authority has established dates for submitting semiannual reports pursuant to 40 CFR 70.6(a)(3)(iii)(A) or 40 CFR 71.6(a)(3)(iii)(A), you may submit the first and subsequent compliance reports according to the dates the permitting authority has established instead of according to the dates in paragraphs (a)(1) through (4) of this section.
(b) Compliance report contents. Each compliance report must include the information in paragraphs (b)(1) through (8) of this section, as applicable.
(1) Company name and address.
(2) On or before January 25, 2021, for affected sources that commenced construction or reconstruction on or before September 25, 2019, statement by a responsible official, with the official's name, title, and signature, certifying the truth, accuracy, and completeness of the content of the report. After January 25, 2021, for affected sources that commenced construction or reconstruction on or before September 25, 2019, and after July 28, 2020, or upon start-up, which ever date is later, for affected sources that commenced construction or reconstruction after September 25, 2019, statement by a responsible official, with the official's name, title, and signature, certifying the truth, accuracy, and completeness of the content of the report. If your report is submitted via CEDRI, the certifier's electronic signature during the submission process replaces the requirement in this paragraph (b)(2).
(3) On or before January 25, 2021, for affected sources that commenced construction or reconstruction on or before September 25, 2019, date of report and beginning and ending dates of the reporting period. After January 25, 2021, for affected sources that commenced construction or reconstruction on or before September 25, 2019, and after July 28, 2020, or upon start-up, which ever date is later, for affected sources that commenced construction or reconstruction after September 25, 2019, date of report and beginning and ending dates of the reporting period. You are no longer required to provide the date of report when the report is submitted via CEDRI.
(4) On or before January 25, 2021, for affected sources that commenced construction or reconstruction on or before September 25, 2019, if you had a startup, shutdown, or malfunction during the reporting period and you took actions consistent with your startup, shutdown, and malfunction plan, the compliance report must include the information in § 63.10(d)(5)(i). A startup, shutdown, and malfunction plan and the information in § 63.10(d)(5)(i) is not required after January 25, 2021, for affected sources that commenced construction or reconstruction on or before September 25, 2019, and is not required after July 28, 2020, for affected sources that commenced construction or reconstruction after September 25, 2019.