§ 63.567 Recordkeeping and reporting requirements.
(a) The owner or operator of an affected source shall fulfill all reporting and recordkeeping requirements in §§ 63.9 and 63.10 of subpart A of this part in accordance with the provisions for applicability of subpart A to this subpart in Table 1 of § 63.560 and fulfill all reporting and recordkeeping requirements in this section. These reports will be made to the Administrator at the appropriate address identified in § 63.13 of subpart A of this part.
(1) Reports required by subpart A and this section may be sent by U.S. mail, facsimile (fax), or by another courier.
(i) Submittals sent by U.S. mail shall be postmarked on or before the specified date.
(ii) Submittals sent by other methods shall be received by the Administrator on or before the specified date.
(2) If acceptable to both the Administrator and the owner or operator of a source, reports may be submitted on electronic media.
(b) Notification requirements. The owner or operator of an affected source shall fulfill all notification requirements in § 63.9 of subpart A of this part in accordance with the provisions for applicability of that section to this subpart in Table 1 of § 63.560 and the notification requirements in this paragraph.
(1) Applicability. If a source that otherwise would not be subject to the emissions standards subsequently increases its HAP emissions calculated on a 24-month annual average basis after September 19, 1997 or increases its annual HAP emissions after September 20, 1999 or subsequently increases its gasoline or crude loading throughput calculated on a 24-month annual average basis after September 19, 1996 or increases its gasoline or crude loading annual throughput after September 21, 1998 such that the source becomes subject to the emissions standards, such source shall be subject to the notification requirements of § 63.9 of subpart A of this part and the notification requirements of this paragraph.
(2) Initial notification for sources with startup before the effective date. The owner or operator of a source with initial startup before the effective date shall notify the Administrator in writing that the source is subject to the relevant standard. The notification shall be submitted not later than 365 days after the effective date of the emissions standards or no later than 120 days after the source becomes subject to this subpart, whichever is later, and shall provide the following information:
(i) The name and address of the owner or operator;
(ii) The address (i.e., physical location) of the source;
(iii) An identification of this emissions standard that is the basis of the notification and the source's compliance date;
(iv) A brief description of the nature, size, design, and method of operation of the source;
(v) A statement that the source is a major source.
(3) Initial notification for sources with startup after the effective date. The owner or operator of a new or reconstructed source or a source that has been reconstructed such that it is subject to the emissions standards that has an initial startup after the effective date but before the compliance date, and for which an application for approval of construction or reconstruction is not required under § 63.5(d) of subpart A of this part and § 63.566 of this subpart, or a sources which reclassifies to major source status after the effective date, shall notify the Administrator in writing that the source is subject to the standard no later than 365 days, 120 days after initial startup, or no later than 120 days after the source becomes subject to this subpart, whichever occurs before notification of the initial performance test in § 63.9(e) of subpart A of this part. The notification shall provide all the information required in paragraph (b)(2) of this section, delivered or postmarked with the notification required in paragraph (b)(4) of this section.