§ 63.5545 What are my monitoring installation, operation, and maintenance requirements?
(a) For each CMS required in this section, you must develop and make available for inspection by the permitting authority, upon request, a site-specific monitoring plan that addresses the provisions in paragraphs (a)(1) through (3) of this section.
(1) Installation of the CMS sampling probe or other interface at a measurement location relative to each affected process unit such that the measurement is representative of control of the exhaust emissions (e.g., on or downstream of the last control device);
(2) Performance and equipment specifications for the sample interface, the pollutant concentration or parametric signal analyzer, and the data collection and reduction system; and
(3) Performance evaluation procedures and acceptance criteria (e.g., calibrations).
(b) In your site-specific monitoring plan, you must also address the provisions in paragraphs (b)(1) through (3) of this section.
(1) Ongoing operation and maintenance procedures in accordance with the general requirements of §§ 63.8(c)(3) and (4)(ii), 63.5515(b), and 63.5580(c)(6);
(2) Ongoing data quality assurance procedures in accordance with the general requirements of § 63.8(d)(2); and