§ 63.481 Compliance dates and relationship of this subpart to existing applicable rules.
(a) Affected sources are required to achieve compliance on or before the dates specified in paragraphs (b) through (d) of this section. Paragraph (e) of this section provides information on requesting compliance extensions. Paragraphs (f) through (l) of this section discuss the relationship of this subpart to subpart A and to other applicable rules. Where an override of another authority of the Act is indicated in this subpart, only compliance with the provisions of this subpart is required. Paragraph (m) of this section specifies the meaning of time periods.
(b) New affected sources that commence construction or reconstruction after June 12, 1995 shall be in compliance with this subpart upon initial start-up or by June 19, 2000, whichever is later.
(c) With the exceptions provided in paragraphs (c)(1) through (3) of this section, existing affected sources shall be in compliance with this subpart no later than June 19, 2001, as provided in § 63.6(c), unless an extension has been granted as specified in paragraph (e) of this section.
(1) Existing affected sources producing epichlorohydrin elastomer, butyl rubber, neoprene rubber, and nitrile butadiene rubber shall be in compliance with the applicable emission limitation in § 63.494(a)(4) no later than April 23, 2012.
(2) Existing affected sources producing butyl rubber and ethylene propylene rubber shall be in compliance with § 63.485(q)(1) no later than April 23, 2012.
(3) Compliance with § 63.502 is covered by paragraph (d) of this section.
(d) Except as provided for in paragraphs (d)(1) through (d)(6) of this section, existing affected sources shall be in compliance with § 63.502 no later than July 31, 1997, unless an extension has been granted pursuant to paragraph (e) of this section.
(1) Compliance with the compressor provisions of § 63.164 shall occur no later than September 5, 1997 for any compressor meeting one or more of the criteria in paragraphs (d)(1)(i) through (d)(1)(iv) of this section, if the work can be accomplished without a process unit shutdown, as defined in § 63.161.
(i) The seal system will be replaced;
(ii) A barrier fluid system will be installed;
(iii) A new barrier fluid will be utilized which requires changes to the existing barrier fluid system; or
(iv) The compressor will be modified to permit connecting the compressor to a fuel gas system or closed vent system, or be modified so that emissions from the compressor can be routed to a process.
(2) Compliance with the compressor provisions of § 63.164 shall occur no later than March 5, 1998, for any compressor meeting all the criteria in paragraphs (d)(2)(i) through (d)(2)(iv) of this section.