§ 97.121 Submission of CAIR permit applications.
(a) Duty to apply. The CAIR designated representative of any CAIR NOX source required to have a title V operating permit shall submit to the permitting authority a complete CAIR permit application under § 97.122 for the source covering each CAIR NOX unit at the source at least 18 months (or such lesser time provided by the permitting authority) before the later of January 1, 2009 or the date on which the CAIR NOX unit commences commercial operation, except as provided in § 97.183(a).