§ 93.125 Enforceability of design concept and scope and project-level mitigation and control measures.
(a) Prior to determining that a transportation project is in conformity, the MPO, other recipient of funds designated under title 23 U.S.C. or the Federal Transit Laws, FHWA, or FTA must obtain from the project sponsor and/or operator written commitments to implement in the construction of the project and operation of the resulting facility or service any project-level mitigation or control measures which are identified as conditions for NEPA process completion with respect to local CO, PM10, or PM2.5 impacts. Before a conformity determination is made, written commitments must also be obtained for project-level mitigation or control measures which are conditions for making conformity determinations for a transportation plan or TIP and are included in the project design concept and scope which is used in the regional emissions analysis required by §§ 93.118 (“Motor vehicle emissions budget”) and 93.119 (“Interim emissions in areas without motor vehicle emissions budgets”) or used in the project-level hot-spot analysis required by § 93.116.