§ 65.5 Reporting requirements.
(a) Required reports. Each owner or operator of a regulated source subject to this subpart shall submit the following reports, as applicable:
(1) A Notification of Initial Startup described in paragraph (b) of this section.
(2) An Initial Notification for Part 65 Applicability described in paragraph (c) of this section.
(3) An Initial Compliance Status Report described in paragraph (d) of this section.
(4) Periodic reports described in paragraph (e) of this section.
(5) Other reports shall be submitted as specified elsewhere in this part.
(6) Startup, Shutdown, and Malfunction Reports described in § 65.6(c).
(b) Notification of Initial Startup—(1) Contents. Any owner or operator of a regulated source which elects to comply with this part at initial startup shall send the Administrator written notification of the actual date of initial startup of a regulated source.
(2) Due date. The notification of the actual date of initial startup shall be postmarked within 15 days after such date.
(c) Initial Notification for Part 65 Applicability. Owners or operators of regulated sources that have been subject to a 40 CFR part 60, 61, or 63 standard, and who wish to comply with this part, and who are not operating the regulated source under an approved title V permit shall notify the Administrator of their intent. The notice shall include the information specified in paragraphs (c)(1) through (7) of this section, as applicable, and may accompany the application for a construction permit for the regulated source. This notification may be waived by the Administrator.
(1) Identification of the storage vessels subject to subpart C of this part.
(2) Identification of the process vents subject to subpart D of this part, including process vent group status as specified in § 65.62(a).
(3) Identification of the process vents subject to 40 CFR part 60, subpart DDD, complying with requirements of subpart G of this part.
(4) Identification of the transfer racks subject to subpart E of this part.
(5) For equipment leaks, identification of the process units subject to subpart F of this part.
(6) The proposed implementation schedule specified in § 65.1(f)(1) for sources identified in paragraphs (c)(1) through (5) of this section.