§ 63.11509 What are my notification, reporting, and recordkeeping requirements?
(a) If you own or operate an affected source, as defined in § 63.11505(a), “What parts of my plant does this subpart cover?”, you must submit an Initial Notification in accordance with paragraphs (a)(1) through (4) of this section by the dates specified.
(1) The Initial Notification must include the information specified in § 63.9(b)(2)(i) through (iv) of the General Provisions of this part.
(2) The Initial Notification must include a description of the compliance method (e.g., use of wetting agent/fume suppressant) for each affected source.
(3) If you start up your affected source on or before July 1, 2008, you must submit an Initial Notification not later than 120 calendar days after July 1, 2008, or no later than 120 days after the source becomes subject to this subpart, whichever is later.
(4) If you startup your new affected source after July 1, 2008, you must submit an Initial Notification when you become subject to this subpart.
(b) If you own or operate an affected source, you must submit a Notification of Compliance Status in accordance with paragraphs (b)(1) through (3) of this section.
(1) The Notification of Compliance Status must be submitted before the close of business on the compliance date specified in § 63.11506, “What are my compliance dates?”
(2) The Notification of Compliance Status must include the items specified in paragraphs (b)(2)(i) through (iv) of this section.
(i) List of affected sources and the plating and polishing metal HAP used in, or emitted by, those sources.