§ 61.155 Standard for operations that convert asbestos-containing waste material into nonasbestos (asbestos-free) material.
Each owner or operator of an operation that converts RACM and asbestos-containing waste material into nonasbestos (asbestos-free) material shall:
(a) Obtain the prior written approval of the Administrator to construct the facility. To obtain approval, the owner or operator shall provide the Administrator with the following information:
(1) Application to construct pursuant to § 61.07.
(2) In addition to the information requirements of § 61.07(b)(3), a
(i) Description of waste feed handling and temporary storage.
(ii) Description of process operating conditions.
(iii) Description of the handling and temporary storage of the end product.
(iv) Description of the protocol to be followed when analyzing output materials by transmission electron microscopy.
(3) Performance test protocol, including provisions for obtaining information required under paragraph (b) of this section.
(4) The Administrator may require that a demonstration of the process be performed prior to approval of the application to construct.
(b) Conduct a start-up performance test. Test results shall include:
(1) A detailed description of the types and quantities of nonasbestos material, RACM, and asbestos-containing waste material processed, e.g., asbestos cement products, friable asbestos insulation, plaster, wood, plastic, wire, etc. Test feed is to include the full range of materials that will be encountered in actual operation of the process.