§ 60.302 Standard for particulate matter.
(a) On and after the 60th day of achieving the maximum production rate at which the affected facility will be operated, but no later than 180 days after initial startup, no owner or operator subject to the provisions of this subpart shall cause to be discharged into the atmosphere any gases which exhibit greater than 0 percent opacity from any:
(1) Column dryer with column plate perforation exceeding 2.4 mm diameter (ca. 0.094 inch).
(2) Rack dryer in which exhaust gases pass through a screen filter coarser than 50 mesh.