§ 35.6805 Contents of an SSC.
The SSC must include the following provisions:
(a) General authorities, which documents the relevant statutes and regulations (of each government entity that is a party to the contract) governing the contract.
(b) Purpose of the SSC, which describes the response activities to be conducted and the benefits to be derived.
(c) Negation of agency relationship between the signatories, which states that no signatory of the SSC can represent or act on the behalf of any other signatory in any matter associated with the SSC.
(d) A site description, pursuant to § 35.6105(a)(2)(i).
(e) A site-specific Statement of Work, pursuant to § 35.6105(a)(2)(ii) and a statement of whether the contract constitutes an initial SSC or an amendment to an existing contract.
(f) A statement of intention to follow EPA policy and guidance.
(g) A project schedule to be prepared during response activities.
(h) A statement designating a primary contact for each party to the contract, which designates representatives to act on behalf of each signatory in the implementation of the contract. This statement must document the authority of each project manager to approve modifications to the project so long as such changes are within the scope of the contract and do not significantly impact the SSC.
(i) The CERCLA assurances, as appropriate, described as follows: