Primary nonferrous smelter orders

42 U.S. Code § 7419. Primary nonferrous smelter orders

(a) Issuance; hearing; enforcement orders; statement of grounds for application; findings
(1) Upon application by the owner or operator of a primary nonferrous smelter, a primary nonferrous smelter order under subsection (b) may be issued—
(A)
by the Administrator, after thirty days’ notice to the State, or
(B)
by the State in which such source is located, but no such order issued by the State shall take effect until the Administrator determines that such order has been issued in accordance with the requirements of this chapter.
Not later than ninety days after submission by the State to the Administrator of notice of the issuance of a primary nonferrous smelter order under this section, the Administrator shall determine whether or not such order has been issued by the State in accordance with the requirements of this chapter. If the Administrator determines that such order has not been issued in accordance with such requirements, he shall conduct a hearing respecting the reasonably available control technology for primary nonferrous smelters.
(2)
(A)
An order issued under this section to a primary nonferrous smelter shall be referred to as a “primary nonferrous smelter order”. No primary nonferrous smelter may receive both an enforcement order under section 7413(d) [1] of this title and a primary nonferrous smelter order under this section.
(B)
Before any hearing conducted under this section, in the case of an application made by the owner or operator of a primary nonferrous smelter for a second order under this section, the applicant shall furnish the Administrator (or the State as the case may be) with a statement of the grounds on which such application is based (including all supporting documents and information). The statement of the grounds for the proposed order shall be provided by the Administrator or the State in any case in which such State or Administrator is acting on its own initiative. Such statement (including such documents and information) shall be made available to the public for a thirty-day period before such hearing and shall be considered as part of such hearing. No primary nonferrous smelter order may be granted unless the applicant establishes that he meets the conditions required for the issuance of such order (or the Administrator or State establishes the meeting of such conditions when acting on their own initiative).
(C)
Any decision with respect to the issuance of a primary nonferrous smelter order shall be accompanied by a concise statement of the findings and of the basis of such findings.