§ 35.2118 Preaward costs.
(a) EPA will not award grant assistance for Step 2 + 3 and Step 3 work performed before award of grant assistance for that project, except:
(1) In emergencies or instances where delay could result in significant cost increases, the Regional Administrator may approve preliminary building work (such as procurement of major equipment requiring long lead times, field testing of innovative and alternative technologies, minor sewer rehabilitation, acquisition of eligible land or an option for the purchase of eligible land or advance building on minor portions of treatment works) after completion of the environmental review as required by § 35.2113.