Permits for treatment, storage, or disposal of hazardous waste
Don't show this message again
(a) Permit requirements
Not later than eighteen months after October 21, 1976, the Administrator shall promulgate regulations requiring each person owning or operating an existing facility or planning to construct a new facility for the treatment, storage, or disposal of hazardous waste identified or listed under this subchapter to have a permit issued pursuant to this section. Such regulations shall take effect on the date provided in section 6930 of this title and upon and after such date the treatment, storage, or disposal of any such hazardous waste and the construction of any new facility for the treatment, storage, or disposal of any such hazardous waste is prohibited except in accordance with such a permit. No permit shall be required under this section in order to construct a facility if such facility is constructed pursuant to an approval issued by the Administrator under section 2605(e) of title 15 for the incineration of polychlorinated biphenyls and any person owning or operating such a facility may, at any time after operation or construction of such facility has begun, file an application for a permit pursuant to this section authorizing such facility to incinerate hazardous waste identified or listed under this subchapter.
(b) Requirements of permit applicationEach application for a permit under this section shall contain such information as may be required under regulations promulgated by the Administrator, including information respecting—
(1)
estimates with respect to the composition, quantities, and concentrations of any hazardous waste identified or listed under this subchapter, or combinations of any such hazardous waste and any other solid waste, proposed to be disposed of, treated, transported, or stored, and the time, frequency, or rate of which such waste is proposed to be disposed of, treated, transported, or stored; and
(2)
the site at which such hazardous waste or the products of treatment of such hazardous waste will be disposed of, treated, transported to, or stored.
(c) Permit issuance
(1)
Upon a determination by the Administrator (or a State, if applicable), of compliance by a facility for which a permit is applied for under this section with the requirements of this section and section 6924 of this title, the Administrator (or the State) shall issue a permit for such facilities. In the event permit applicants propose modification of their facilities, or in the event the Administrator (or the State) determines that modifications are necessary to conform to the requirements under this section and section 6924 of this title, the permit shall specify the time allowed to complete the modifications.
(2)
(A)
(i)
Not later than the date four years after November 8, 1984, in the case of each application under this subsection for a permit for a land disposal facility which was submitted before such date, the Administrator shall issue a final permit pursuant to such application or issue a final denial of such application.
(ii)
Not later than the date five years after November 8, 1984, in the case of each application for a permit under this subsection for an incinerator facility which was submitted before such date, the Administrator shall issue a final permit pursuant to such application or issue a final denial of such application.
(B)
Not later than the date eight years after November 8, 1984, in the case of each application for a permit under this subsection for any facility (other than a facility referred to in subparagraph (A)) which was submitted before such date, the Administrator shall issue a final permit pursuant to such application or issue a final denial of such application.
(C) The time periods specified in this paragraph shall also apply in the case of any State which is administering an authorized hazardous waste program under section 6926 of this title. Interim status under subsection (e) shall terminate for each facility referred to in subparagraph (A)(ii) or (B) on the expiration of the five- or eight-year period referred to in subparagraph (A) or (B), whichever is applicable, unless the owner or operator of the facility applies for a final determination regarding the issuance of a permit under this subsection within—
(i)
two years after November 8, 1984 (in the case of a facility referred to in subparagraph (A)(ii)), or
(ii)
four years after November 8, 1984 (in the case of a facility referred to in subparagraph (B)).