§ 70.6 Permit content.
(a) Standard permit requirements. Each permit issued under this part shall include the following elements:
(1) Emissions limitations and standards, including those operational requirements and limitations that assure compliance with all applicable requirements at the time of permit issuance. Such requirements and limitations may include ARMs identified by the source in its part 70 permit application as approved by the permitting authority, provided that no ARM shall contravene any terms needed to comply with any otherwise applicable requirement or requirement of this part or circumvent any applicable requirement that would apply as a result of implementing the ARM.
(i) The permit shall specify and reference the origin of and authority for each term or condition, and identify any difference in form as compared to the applicable requirement upon which the term or condition is based.
(ii) The permit shall state that, where an applicable requirement of the Act is more stringent than an applicable requirement of regulations promulgated under title IV of the Act, both provisions shall be incorporated into the permit and shall be enforceable by the Administrator.
(iii) If an applicable implementation plan allows a determination of an alternative emission limit at a part 70 source, equivalent to that contained in the plan, to be made in the permit issuance, renewal, or significant modification process, and the State elects to use such process, any permit containing such equivalency determination shall contain provisions to ensure that any resulting emissions limit has been demonstrated to be quantifiable, accountable, enforceable, and based on replicable procedures.
(2) Permit duration. The permitting authority shall issue permits for a fixed term of 5 years in the case of affected sources, and for a term not to exceed 5 years in the case of all other sources. Notwithstanding this requirement, the permitting authority shall issue permits for solid waste incineration units combusting municipal waste subject to standards under section 129(e) of the Act for a period not to exceed 12 years and shall review such permits at least every 5 years.
(3) Monitoring and related recordkeeping and reporting requirements. (i) Each permit shall contain the following requirements with respect to monitoring:
(A) All monitoring and analysis procedures or test methods required under applicable monitoring and testing requirements, including part 64 of this chapter and any other procedures and methods that may be promulgated pursuant to sections 114(a)(3) or 504(b) of the Act. If more than one monitoring or testing requirement applies, the permit may specify a streamlined set of monitoring or testing provisions provided the specified monitoring or testing is adequate to assure compliance at least to the same extent as the monitoring or testing applicable requirements that are not included in the permit as a result of such streamlining;
(B) Where the applicable requirement does not require periodic testing or instrumental or noninstrumental monitoring (which may consist of recordkeeping designed to serve as monitoring), periodic monitoring sufficient to yield reliable data from the relevant time period that are representative of the source's compliance with the permit, as reported pursuant to paragraph (a)(3)(iii) of this section. Such monitoring requirements shall assure use of terms, test methods, units, averaging periods, and other statistical conventions consistent with the applicable requirement. Recordkeeping provisions may be sufficient to meet the requirements of this paragraph (a)(3)(i)(B) of this section; and
(C) As necessary, requirements concerning the use, maintenance, and, where appropriate, installation of monitoring equipment or methods.
(ii) With respect to recordkeeping, the permit shall incorporate all applicable recordkeeping requirements and require, where applicable, the following: