§ 146.8 Mechanical integrity.
(a) An injection well has mechanical integrity if:
(1) There is no significant leak in the casing, tubing or packer; and
(2) There is no significant fluid movement into an underground source of drinking water through vertical channels adjacent to the injection well bore.
(b) One of the following methods must be used to evaluate the absence of significant leaks under paragraph (a)(1) of this section:
(1) Following an initial pressure test, monitoring of the tubing-casing annulus pressure with sufficient frequency to be representative, as determined by the Director, while maintaining an annulus pressure different from atmospheric pressure measured at the surface;
(2) Pressure test with liquid or gas; or
(3) Records of monitoring showing the absence of significant changes in the relationship between injection pressure and injection flow rate for the following Class II enhanced recovery wells: