§ 2200.4 Computing time.
(a) Computation. The following rules apply in computing any time period specified in these rules or by any order that does not specify a method of computing time.
(1) Period stated in days or longer unit. When the period is stated in days or a longer unit of time:
(i) Exclude the day of the event that triggers the period;
(ii) Count every day, including intermediate Saturdays, Sundays, and Federal holidays; and
(iii) Include the last day of the period, but if the last day is a Saturday, Sunday, or Federal holiday, the period continues to run until the end of the next day that is not a Saturday, Sunday, or Federal holiday.
(2) Period stated in working days. When the period is stated in working days, count every day except intermediate Saturdays, Sundays, and Federal holidays.