§ 63.1422 Compliance dates and relationship of this rule to existing applicable rules.
(a) [Reserved]
(b) New affected sources that commence construction or reconstruction after September 4, 1997 shall be in compliance with this subpart (except § 63.1434(c)(3)) upon initial start-up or by June 1, 1999, whichever is later. New affected sources that commenced construction or reconstruction after September 4, 1997, but on or before January 9, 2012, shall be in compliance with the pressure relief device monitoring requirements of § 63.1434(c)(3) by March 27, 2017. New affected sources that commence construction or reconstruction after January 9, 2012, shall be in compliance with the pressure relief device monitoring requirements of § 63.1434(c)(3) upon initial startup or by March 27, 2014, whichever is later.
(c) Existing affected sources shall be in compliance with this subpart (except for § 63.1434 for which compliance is covered by paragraph (d) of this section) no later than June 1, 2002, as provided in § 63.6(c), unless an extension has been granted as specified in paragraph (e) of this section.
(d) Except as provided for in paragraphs (d)(1) through (6) of this section, existing affected sources shall be in compliance with § 63.1434 no later than December 1, 1999 unless an extension has been granted as specified in paragraph (e) of this section.
(1) Compliance with the compressor provisions of § 63.164 shall occur no later than June 1, 2000 for any compressor meeting one or more of the criteria in paragraphs (d)(1)(i) through (iv) of this section, if the work can be accomplished without a process unit shutdown, as defined in § 63.161.
(i) The seal system will be replaced.
(ii) A barrier fluid system will be installed.
(iii) A new barrier fluid will be utilized which requires changes to the existing barrier fluid system.
(iv) The compressor shall be modified to permit connecting the compressor to a closed vent system.
(2) Compliance with the compressor provisions of § 63.164 shall occur no later than December 1, 2000, for any compressor meeting all the criteria in paragraphs (d)(2)(i) through (iv) of this section.
(i) The compressor meets one or more of the criteria specified in paragraphs (d)(1)(i) through (iv) of this section.
(ii) The work can be accomplished without a process unit shutdown as defined in § 63.161.
(iii) The additional time is necessary, due to the unavailability of parts beyond the control of the owner or operator.
(iv) The owner or operator submits the request for a compliance extension to the appropriate U.S. Environmental Protection Agency Regional Office at the addresses listed in § 63.13 no later than 45 days before December 1, 1999. The request for a compliance extension shall contain the information specified in § 63.6(i)(6)(i)(A) and (B). Unless the EPA Regional Office objects to the request for a compliance extension within 30 days after receipt of the request, the request shall be deemed approved.