§ 63.1364 Compliance dates.
(a) Compliance dates for existing sources. (1) An owner or operator of an existing affected source must comply with the provisions in this subpart (except § 63.1363(b)(4)(iii)) by December 23, 2003. Compliance with the pressure relief device monitoring provisions of § 63.1363(b)(4)(iii) shall occur no later than March 27, 2017.
(2) Pursuant to section 112(i)(3)(B) of the CAA, an owner or operator of an existing source may request an extension of up to 1 additional year to comply with the provisions of this subpart if the additional time is needed for the installation of controls.