§ 97.283 Applying for CAIR opt-in permit.
(a) Applying for initial CAIR opt-in permit. The CAIR designated representative of a unit meeting the requirements for a CAIR SO2 opt-in unit in § 97.280 may apply for an initial CAIR opt-in permit at any time, except as provided under § 97.286(f) and (g), and, in order to apply, must submit the following:
(1) A complete CAIR permit application under § 97.222;
(2) A certification, in a format specified by the permitting authority, that the unit:
(i) Is not a CAIR SO2 unit under § 97.204 and is not covered by a retired unit exemption under § 97.205 that is in effect;
(ii) Is not covered by a retired unit exemption under § 72.8 of this chapter that is in effect;