§ 72.83 Administrative permit amendment.
(a) Acid Rain permit revisions that shall follow the administrative permit amendment procedures are:
(1) Activation of a compliance option conditionally approved by the permitting authority; provided that all requirements for activation under subpart D of this part are met;
(2) Changes in the designated representative or alternative designated representative; provided that a new certificate of representation is submitted;
(3) Correction of typographical errors;
(4) Changes in names, addresses, or telephone or facsimile numbers;
(5) Changes in the owners or operators; provided that a new certificate of representation is submitted within 30 days;
(6)
(i) Termination of a compliance option in the permit; provided that all requirements for termination under subpart D of this part are met and this procedure shall not be used to terminate a repowering plan after December 31, 1999 or a Phase I extension plan;